The Buildout Registry · New Jersey

Vineland

Nebius · Vineland, Cumberland County, New Jersey

Verified by Neocloud GroupChecked against 2 sources, including primary filings and releases
Open on the map →
400 MW
Gross planned
50 MW
Energized today
2025-Q4
First power
PJM
Grid region · location approximate
In brief

What makes it notable.

  1. Built to bypass the PJM queue: on-site natural gas generation supplies about 85% of power under an NJDEP air permit, with Vineland Municipal Electric Utility providing roughly 15% as grid and backup.
  2. 50 MW is current gross capacity against 400 MW planned, with first power in the fourth quarter of 2025 and full buildout in 2026.
  3. A new-build facility from Nebius, using dedicated NVIDIA GPU infrastructure, and operated by Nebius itself as the neocloud, with the gas-fed design chosen to avoid waiting on grid interconnection.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
On-site natural gas generation (behind-the-meter), Vineland Municipal Electric Utility (VMEU)
Site and build
Nebius (self-build)
Compute
NVIDIA
Cloud operator
Nebius
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2025-Q4First power
  2. 2026Full buildout
  3. Oct 2026Today
The detail

Each party's role.

Power

On-site natural gas generation (behind-the-meter). Primary supply ~85%; built to bypass the PJM queue

Power

Vineland Municipal Electric Utility (VMEU). NJ municipal utility; ~15% grid/backup

Site and build

Nebius (self-build). New-build data center reported

Compute

NVIDIA. Dedicated GPU infrastructure reported

Cloud operator

Nebius. Neocloud operator

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in New Jersey?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in New Jersey can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →