What makes it notable.

  1. Georgia Power has committed 216 MW in total to this campus, of which 154 MW is critical IT across four buildings totaling 747,787 square feet on 72 acres.
  2. Site prep began in September 2024 with Evans General Contractors, and Corgan and DLB Associates handle design and engineering.
  3. First power is now estimated for 2027, slipped from a fourth-quarter 2025 target because of federal and state water permitting.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Georgia Power
Site and build
Evans General Contractors, Corgan / DLB Associates
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Oct 2026Today
  2. 2027First powerestimated; slipped from the 4Q 2025 target on federal/state water permitting
  3. not disclosedFull buildout
The detail

Each party's role.

Power

Georgia Power. Utility; 216 MW total power committed (154 MW critical IT across 4 buildings per the issuer campus page)

Site and build

Evans General Contractors. General contractor; 747,787 sq ft at full build on 72 acres; site prep began Sept 2024 reported

Site and build

Corgan / DLB Associates. Design and engineering reported

Compute

Not disclosed. Tenant-controlled inferred

Cloud operator

Not disclosed. Tenant-controlled; the campus ties into DC BLOX's Atlanta dark fiber ring and Myrtle Beach cable landing station inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Georgia?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Georgia can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →