40 MW
Critical IT planned
0 MW
Energized today
2026-Q2/Q3 expected
First power
SERC
Grid region · location approximate
In brief

What makes it notable.

  1. A retrofit of a roughly 1 million square foot former textile plant on 96 acres, bought for $45M, to Tier 3-equivalent specs: up to 150 kW per cabinet, N+1 cooling and a target PUE of 1.3.
  2. Duke Energy Carolinas staged power at 24 MW, 40 MW and 99 MW within four years, with work done to deliver the initial 54 MW gross as of May 2026.
  3. Feasibility is about 200 MW, with a company target near 300 MW gross over time. Delivery slipped on a switchgear supply issue and was guided to the second or third quarter of 2026.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Duke Energy Carolinas
Site and build
Enovum Data Centers (WhiteFiber subsidiary)
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2026-Q2/Q3 expectedFirst powerguided Q2 2026 delivery to Nscale after a switchgear supply-chain slip; not yet confirmed in service
  2. Oct 2026Today
  3. ~2029Full buildout99 MW within 4 years of the May 2025 Duke letter agreement
The detail

Each party's role.

Power

Duke Energy Carolinas. Utility; 99 MW letter agreement filed as an SEC exhibit (24 MW ~Sep 2025, 40 MW ~Apr 2026, 99 MW within 4 years); work completed to deliver the initial 54 MW gross as of May 2026; feasibility ~200 MW, company targets ~300 MW gross over time

Site and build

Enovum Data Centers (WhiteFiber subsidiary). In-house developer retrofitting the ~1M sq ft former Unifi textile plant (96 acres, bought $45M) to Tier 3-equivalent, up to 150 kW/cabinet, N+1 cooling, target PUE 1.3

Compute

Not disclosed. Tenant (Nscale) deploys its own GPU systems inferred

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in North Carolina?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in North Carolina can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →