The Buildout Registry · Texas

Black Pearl

Cipher Mining · Wink, Winkler County, Texas

Verified by Neocloud GroupChecked against 3 sources, including primary filings and releases
Open on the map →
216 MW
Critical IT planned
0 MW
Energized today
2026-08
First power
ERCOT
Grid region · location approximate
In brief

What makes it notable.

  1. A turnkey shell in Wink, Texas, where the owner supplies space and power and the tenant runs its own stack, with up to 300 MW of ERCOT interconnection approved.
  2. The plan is 300 MW gross and 216 MW critical. First capacity was delivered in August 2026, two months early.
  3. An updated phased delivery schedule was agreed in October 2026, with construction status reported as of September 30, 2026. Later phase dates are not disclosed.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
ERCOT
Site and build
EPC / cooling integrator undisclosed
Compute
Undisclosed (AWS tenant-supplied)
Cloud operator
Cipher Mining
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2026-08First powerfirst capacity delivered two months early; rent commenced
  2. Updated phased schedule agreed with AWSFull buildoutOct 2026); dates not disclosed
  3. Oct 2026Today
The detail

Each party's role.

Power

ERCOT. Grid interconnection, up to 300 MW approved

Site and build

EPC / cooling integrator undisclosed. Lease specifies both air and liquid cooling to the racks; retrofit of a prior mining building for AI/HPC, contractor not disclosed inferred

Compute

Undisclosed (AWS tenant-supplied). AWS-supplied; maybe Trainium, not NVIDIA inferred

Cloud operator

Cipher Mining. Owner/operator of the turnkey shell (space and power); AWS runs its own stack

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Texas?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Texas can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →