The Buildout Registry · Texas

Beacon Point

Hut 8 · Robstown, Nueces County, Texas

Verified by Neocloud GroupChecked against 6 sources, including primary filings and releases
Open on the map →
704 MW
Critical IT planned
0 MW
Energized today
2027-Q1
First power
ERCOT
Grid region · location approximate
In brief

What makes it notable.

  1. A 1,000 MW interconnection agreement with AEP Texas anchors a roughly 521-acre campus, with about 500 MW serving phase one and the remainder under development for phase two.
  2. Two 352 MW phases are both designed to NVIDIA's DSX reference architecture; redesigning the phase one data halls added 57 percent more IT capacity on the same land and utility footprint.
  3. Utility energization is targeted for the first quarter of 2027, phase one halls for the third quarter of 2027, and phase two's first hall for the second quarter of 2028. Jacobs leads EPCM and Vertiv supplies power and cooling.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
AEP Texas (American Electric Power)
Site and build
Jacobs, Vertiv
Compute
NVIDIA
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Oct 2026Today
  2. 2027-Q1First powerinitial utility energization
  3. 2027-Q3Full buildoutphase 1 data hall delivery); 2028-Q2 (phase 2 initial hall delivery
The detail

Each party's role.

Power

AEP Texas (American Electric Power). 1,000 MW interconnection agreement; roughly 500 MW serves phase 1, the remainder under development for phase 2

Site and build

Jacobs. EPCM lead (role expanded mid-2026) for the ~521-acre campus

Site and build

Vertiv. Critical power and cooling infrastructure

Compute

NVIDIA. DSX reference architecture for gigawatt-scale AI infrastructure; both 352 MW phases are designed to it (the phase 1 data hall redesign enabled 57% more IT capacity within the same land and utility footprint)

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Texas?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Texas can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →