The Buildout Registry · Texas

Core Scientific Pecos Campus

Core Scientific · Pecos, Reeves County, Texas

Verified by Neocloud GroupChecked against 7 sources, including primary filings and releases
Open on the map →
1,000 MW
Critical IT planned
0 MW
Energized today
Under construction
Stage
ERCOT
Grid region · location approximate
In brief

What makes it notable.

  1. A conversion of a 300 MW bitcoin mining campus into AI data halls, self-performed by Core Scientific, with 300 MW of TNMP utility capacity energized in far-west Texas.
  2. ERCOT has conditionally approved the existing 300 MW in Batch Zero as Base Load, plus a further 300 MW as Studied Load. Final allocation and load ramp await the end of Batch Zero.
  3. The plan expands to 1.5 GW gross and 1,000 MW critical. First hall footings were set and precast walls were arriving as of April 27, 2026.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Texas-New Mexico Power (TNMP), ERCOT
Site and build
Core Scientific (in-house development)
Compute
AMD Instinct GPUs / EPYC CPUs
Cloud operator
AMD ROCm, Core Scientific
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
The detail

Each party's role.

Power

Texas-New Mexico Power (TNMP). T&D utility for the campus: 300 MW of gross utility capacity energized, with an incremental ~300 MW confirmed with the utility but allocation timing undetermined

Power

ERCOT. Independent system operator; TNMP's T&D activities are solely within ERCOT, covering far-west Texas between Midland and El Paso. The existing 300 MW is conditionally approved in Batch Zero as Base Load, Pathway (b); a further 300 MW is conditionally approved as Studied Load. Collateral posted; the final allocation and load ramp await the end of Batch Zero

Site and build

Core Scientific (in-house development). Self-performs siting, design and development, converting a 300 MW bitcoin mining campus into AI data halls; first hall footings set and precast walls arriving as of 2026-04-27. No third-party general contractor is named for the AI build.

Compute

AMD Instinct GPUs / EPYC CPUs. Silicon named at partnership level; no filing assigns specific hardware to Pecos inferred

Cloud operator

AMD ROCm. Software stack named alongside Instinct and EPYC in the deployment collaboration; not site-specific inferred

Cloud operator

Core Scientific. Operates and maintains the campus

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Texas?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Texas can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →