The Buildout Registry · Nevada

Vantage NV1

Vantage Data Centers · Storey County, Storey County, Nevada

Verified by Neocloud GroupChecked against 3 sources, including primary filings and releases
Open on the map →
224 MW
Critical IT planned
0 MW
Energized today
2026-Q2
First power
WECC
Grid region · location approximate
In brief

What makes it notable.

  1. A ground-up campus of four multi-story buildings, 1.1 million square feet on 137 acres, with 224 MW of planned critical capacity and a private 500 MW on-site substation.
  2. NV Energy serves it from the ON Line 500 kV regional backbone, though northern Nevada large-load queue pressure is the regional risk.
  3. Cooling is closed-loop chillers with near-zero water use, air plus liquid, at 360 to 720 W per square foot. First power was scheduled for the second quarter of 2026.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
NV Energy
Site and build
Vantage Data Centers
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2026-Q2First powerscheduled; opening not publicly confirmed as of July 2026
  2. Oct 2026Today
  3. not disclosedFull buildoutfour buildings, phased
The detail

Each party's role.

Power

NV Energy. Utility; private 500 MW on-site substation; ON Line 500 kV regional backbone. Northern Nevada large-load queue pressure is the regional risk

Site and build

Vantage Data Centers. Ground-up build: four multi-story buildings, 1.1M sq ft on 137 acres; closed-loop chillers, near-zero water use, air plus liquid cooling, 360-720 W/sq ft

Compute

Not disclosed. Tenant-controlled inferred

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Nevada?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Nevada can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →