The Buildout Registry · Nevada

Fleet Peru Ridge (TRIC)

Fleet Data Centers · Tahoe Reno Industrial Center, Storey County, Nevada

Verified by Neocloud GroupChecked against 4 sources, including primary filings and releases
Open on the map →
200 MW
Critical IT planned
0 MW
Energized today
2027-Q3
First power
WECC
Grid region · location approximate
In brief

What makes it notable.

  1. NV Energy cannot serve the site immediately, so a 218 MW temporary natural gas plant is proposed to bridge interconnection, a first-of-its-kind request in Nevada filed with the PUCN on April 20, 2026.
  2. Permanent utility service is expected in two to three years, supported by a dedicated on-site substation within the project.
  3. Two two-story buildings on 517 acres have been under construction since May 2026, delivering 200 MW critical IT in a single phase with a reported third-quarter 2027 target.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
NV Energy, Peru Ridge Self-Generation Project
Site and build
Fleet Data Centers (build-to-suit)
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. Oct 2026Today
  2. 2027-Q3First powerreported target
  3. 2027Full buildoutsingle phase, 100% pre-leased
The detail

Each party's role.

Power

NV Energy. Utility; cannot serve immediately, permanent service expected in 2 to 3 years; dedicated on-site substation within the bond-financed project reported

Power

Peru Ridge Self-Generation Project. 218 MW temporary natural gas plant to bridge interconnection; PUCN application filed 2026-04-20, a first-of-its-kind request in Nevada reported

Site and build

Fleet Data Centers (build-to-suit). Greenfield on 517 acres; dual two-story buildings under construction since May 2026; GC not named reported

Compute

Not disclosed. Tenant-controlled inferred

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Nevada?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Nevada can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →