The Buildout Registry · Texas

Frontier

Vantage Data Centers · Shackelford County, Shackelford County, Texas

Verified by Neocloud GroupChecked against 5 sources, including primary filings and releases
Open on the map →
1,400 MW
Critical IT planned
0 MW
Energized today
2026-H2
First power
ERCOT
Grid region · location approximate
In brief

What makes it notable.

  1. The primary power plan is off-grid: a behind-the-meter natural gas microgrid using INNIO Jenbacher engines from VoltaGrid, per press reporting citing project documents, though the site sits in ERCOT.
  2. Kiewit is general contractor for 10 buildings totaling 3.7 million square feet on 1,200 acres, with groundbreaking in December 2025 and 1.4 GW of critical IT planned.
  3. The closed-loop chiller design targets racks of 250 kW and above with minimal water use. The first building is targeted for the second half of 2026 and full buildout for 2028.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
VoltaGrid
Site and build
Kiewit
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2026-H2First powerfirst building
  2. Oct 2026Today
  3. 2028Full buildoutreported
The detail

Each party's role.

Power

VoltaGrid. Behind-the-meter on-site natural gas microgrid (INNIO Jenbacher engines) per press reporting citing project documents; the Vantage-VoltaGrid partnership covers 1 GW+ portfolio-wide. ERCOT is the region, the primary supply plan is off-grid reported

Site and build

Kiewit. General contractor: 10 buildings, 3.7M sq ft on 1,200 acres; groundbreaking Dec 2025; closed-loop chiller design for 250kW+ racks with minimal water use reported

Compute

Not disclosed. No compute fleet announced for this campus inferred

Cloud operator

Not disclosed. Operating stack not announced; Oracle-led under the Stargate model inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Texas?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Texas can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →