The Buildout Registry · New Mexico

Project Jupiter (Stargate NM)

BorderPlex Digital Assets / STACK Infrastructure · Santa Teresa, Dona Ana County, New Mexico

Verified by Neocloud GroupChecked against 5 sources, including primary filings and releases
Open on the map →
2,450 MW
At full build
0 MW
Energized today
2026
First power
WECC
Grid region · location approximate
In brief

What makes it notable.

  1. An islanded campus: the on-site microgrid is designed to run on Bloom Energy solid oxide fuel cells, up to 2.45 GW, with battery storage, replacing a withdrawn 2.8 GW gas turbine and diesel plan in April 2026.
  2. STACK Infrastructure is the development and construction partner; heavy construction began in late 2025 and reached a 1,600-person daily onsite peak by April 2026.
  3. Cooling is closed-loop with a one-time fill of non-potable water. The developer targets operations before the end of 2026, with the initial phase on the county timeline for 2028.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Bloom Energy, El Paso Electric
Site and build
STACK Infrastructure
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2026First powerdeveloper target: operations before year end
  2. Oct 2026Today
  3. 2028 initial phase per the county timeline; up to 30 years under the IRBFull buildout
The detail

Each party's role.

Power

Bloom Energy. Solid oxide fuel cells for the on-site microgrid, up to 2.45 GW; replaced the withdrawn 2.8 GW gas turbine and diesel plan in April 2026 reported

Power

El Paso Electric. Local utility territory; the campus is designed to run islanded on its own microgrid with battery storage reported

Site and build

STACK Infrastructure. Development and construction partner; closed-loop cooling with a one-time fill, non-potable water; heavy construction since late 2025 (1,600-person daily onsite peak by April 2026)

Compute

Not disclosed. No chip or fabric vendor disclosed inferred

Cloud operator

Not disclosed. Beyond Oracle Cloud Infrastructure as lessee, no operating stack disclosed inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in New Mexico?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in New Mexico can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →