175 MW
Critical IT planned
31 MW
Energized today
2022
First power
WECC
Grid region · location approximate
In brief

What makes it notable.

  1. Primary power is on-site: a 200 MW natural gas plant with 72 permitted engines, because Rocky Mountain Power cannot fully serve the campus until about 2031.
  2. A 200 MW on-campus substation is in place, with solar planned. The campus is water-free ambient-air design with direct-to-chip cooling and an annualized PUE of 1.18.
  3. Phase 1 opened in September 2022 and 31 MW of critical IT is online. Phases 2 and 3 of 72 MW each target 2026 toward 175 MW on about 100 acres.
Deal anatomy

Six layers, and who holds each.

Every Registry site is read the same way: a campus is real when each layer has a name. Members see the anchor tenant and the capital.

Power
Rocky Mountain Power (PacifiCorp), On-site natural gas generation
Site and build
Novva (BASX Solutions cooling)
Compute
Not disclosed
Cloud operator
Not disclosed
Anchor tenant
Members
Capital
Members
Free for professionals in AI infrastructure.
Timeline

From here to full build.

  1. 2022First powerphase 1 grand opening Sept 2022; some 2025 press says 2023
  2. 2026Full buildoutphases 2 and 3, 72 MW each
  3. Oct 2026Today
The detail

Each party's role.

Power

Rocky Mountain Power (PacifiCorp). Retail utility; on-campus 200 MW substation, but cannot fully serve until ~2031

Power

On-site natural gas generation. On-site primary power: 200 MW gas plant + 72 permitted engines; solar planned

Site and build

Novva (BASX Solutions cooling). Water-free ambient-air design with direct-to-chip cooling (~84% less water than comparable regional data centers, PUE 1.18 annualized); 100-acre, ~1M sq ft campus reported

Compute

Not disclosed. Tenant-controlled inferred

Cloud operator

Not disclosed. Tenant-controlled inferred

Related sites

Nearby in the buildout.

Sources

The record behind this page.

Neocloud Group

Who keeps this record.

Neocloud Group is the advisory firm AI companies bring in to secure data center capacity. The Registry is part of that work.

Need capacity in Utah?

Tell us the megawatts and the date. Within one business day, a first read on which operators and sites in Utah can take you. Hold a powered site there yourself? Tell us about it.

Start a conversation →